Branch County Jail - Coldwater, MI

Scope: The Branch County Jail Project includes construction of a brand-new facility behind the county's current facility. The new county jail will be roughly 41,000 square feet that will include two hundred-twenty (220) beds. Once the new jail is complete, they will demolish the old facility.

Pauly Jail Building Company scope of work included furnishing and installing: modular controls, security electronics, security glass, mesh, enclosures, padded cells, mezzanine, stairs, detention furnishings, detention hardware/ locks, prefabricated modular steel cells, and security hollow metal.

Start Date: 10/2020

Completion Date: 9/2021

Overall Construction Cost: $22,000,000.00

Pauly Jail Building Company Contract Amount: $5,401,480.00

General Contractor: Clark Construction Company | 3535 Moores River Drive | Lansing, MI 48911 | (517) 372-0940 Phone

Security Architect: Byce & Associates | 487 Portage Street | Kalamazoo, MI 49007 | (269) 381-6170 Phone

Sheriff: Sheriff C. John Pollack | 518 Marshall Road | Coldwater, MI 49036 | (517) 278-2325 Phone

 


Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers.

Partners that were a part of this project:

- Accurate Controls, Inc. for Modular Controls & Security Electronics

- Global Security Glazing for Security Glass

- Kane Innovations, Inc. (Kane Detention) for Security Mesh & Enclosures

- Marathon Engineering Corporation for Padded Cells

- Modern Detention Equipment for Mezzanine & Stairs

- Norix Group for Detention Furnishings

- RR Brink Locking Systems, Inc. for Detention Hardware & Locks

- SteelCell of North America, Inc. for Prefabricated Modular Steel Cells

- Titan Steel Door for Security Hollow Metal