Columbus Government Center

Scope: New 8-story courthouse with 6 elevators. Scope consists of installing detention doors, hardware, toilet accessories, glazing, and detention furnishings.

Pauly Jail Building Company was tasked with furnishing and installing security hollow metal doors/frames, modular steel cells, detention furnishings, security mesh, plumbing fixtures, and more.

Overall Construction Cost: $$1,146,096.00

Pauly Jail Building Company Contract Amount: $1,150,171.00

Start Date: 2024

Estimated Completion Date: 2028

General Contractor: Gilbane Building Company | 3350 Peachtree Road 1200 | Atlanta, GA 30326 |

Chief of Police: Stoney Mathis | 510 10th Street | Columbus, Georgia 31902 | 706-653-3205

Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers. 

Partners that are a part of this project include:

Kane Detention for Security Mesh

- Modern Detention Equipment for Detention Furnishings & Equipment

- NORIX for Detention Toilet Accessories

- Titan Steel Door for Security Hollow Metal Doors/Frames, Security Ceilings & Wall Panels