Gibson County Sheriff's Office & Jail - Princeton, IN

Scope: The New Gibson County Sheriff’s Office and Jail will be offering a variety of improvements compared to the county’s old facility. The jail will include a 911 center, amenities for drug and alcohol treatment, and a control room that will allow corrections officers to see all day rooms simultaneously. The facility will be able to house roughly two hundred (200) inmates and is double the size of the old county jail.

Pauly Jail is tasked with furnishing and installing: modular steel cells (52), security glazing, security mesh, detention furnishings, mezzanine, detention equipment, and security hardware.

Start Date: 9/8/2022

Est. Completion Date: 6/2024

Overall Construction Contract Amount: $24,000,000.00

Pauly Jail Building Company Contract Amount: $6,883,000.00

General Contractor: C.H. Garmong & Son, Inc. | 4117 N. St. Joseph Ave. | Evansville, IN 47720

Architect: RQAW Consulting Engineers & Architects | 8770 North Street, Suite 110 | Fishers, IN 46038

Sheriff: Sheriff Timothy Bottoms | 112 E. Emerson Street | Princeton, IN 47670

Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers.

Partners that are a part of this project include:

- Accurate Controls, Inc. for Modular Controls

- Global Security Glazing for Security Glazing

- Kane Detention for Security Mesh

- Marathon Engineering for Padded Cells

- Modern Detention Equipment for Detention Furnishings & Mezzanine

- Norix for Detention Equipment

- RR Brink Locking Systems, Inc. for Security Hardware

- Security Automation Systems for Security Electronics

- SteelCell of North America for Modular Steel Cells

- Titan Steel Door for Security Hollow Metal