Scope: A 52,500 SF addition to the existing jail and the creation of a new juvenile detention center. Work includes detention frames and doors, locks and hardware, exterior and interior windows, detention furnishings, security glazing, and a padded cell.
Pauly Jail Building Company was tasked with furnishing and installing security hollow metal doors/frames, modular steel cells, detention furnishings, security mesh, plumbing fixtures, and more.
Overall Construction Cost: $$2,684,680.00
Pauly Jail Building Company Contract Amount: $2,612,440.00
Start Date: December 2023
Estimated Completion Date: July 2025
General Contractor: Construction Engineers, Inc. | 200 North 69th Street | Grand Forks, ND 58203 |
Architect: Icon Architecture | 4000 Garden View Drive, Suite 101 |Grand Forks, ND 58201 | (701) 772-4266 Phone |
Sheriff: Sheriff Andrew Schneider | 122 South 5th Street Suite 210 | (701) 780-82880 Phone |
Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers.
Partners that are a part of this project include:
- Hope’s Windows for Security Windows
- Kane Detention for Security Mesh
- Marathon Engineering Corporation for Padded Cells
- Modern Detention Equipment for Detention Furnishings & Equipment
- NORIX for Detention Toilet Accessories
- SteelCell World-Class Security Solutions for Modular Steel Cells
- Titan Steel Door for Security Hollow Metal Doors/Frames, Security Ceilings & Wall Panels
- Willoughby Industries for Plumbing Fixtures