Paulding County Adult Detention & Law Enforcement Center - Dallas, GA

Scope: The Paulding County Adult Detention and Law Enforcement Center Design Assist Project is a six hundred sixty (660) bed, 133,000-square-foot facility that will be adjacent to the sheriff's office headquarters. The project includes a new jail, new administrative space for the sheriff's office, and the county government's first dedicated morgue.

Pauly Jail Building Company scope of work included furnishing and installing: two hundred forty (240) modular steel cells, detention hollow metal doors, detention frames, security hardware, locking devices, security glass/ glazing, security electronics, detention furnishings, and detention accessories.

Start Date: 06/13/2018

Est. Completion Date: 2020

Overall Construction Cost: $60,000,000.00

Pauly Jail Building Company Contract Amount: $9,378,300.00

Construction Manager: Turner Construction | 3495 Piedmont Rd. NE Building 11, Suite 700| Atlanta, GA 30305 | (404) 504-3700 Phone

Architects:

     Wakefield Beasley & Associates | 5200 Avalon Blvd. | Alpharetta, GA 30009 | (770) 209-9393 Phone

     TreanorHL | 5250 Avalon Blvd. | Alpharetta, GA 30009 | (678) 297-2929 Phone

Sheriff: Gary Gulledge | 247 Industrial Way N |Dallas, GA 30132 | (770) 443-3010 Phone

 

Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers.

Partners that were a part of this project:

- Accurate Controls, Inc. for Security Electronics

- Global Security Glazing for Security Glass

- Modern Detention Equipment for Detention Furnishings

- Norix Group, Inc. for Detention Accessories

- RR Brink Locking Systems, Inc. for Detention Hardware & Locks

- SteelCell of North America, Inc. for Prefabricated Modular Steel Cells

- Titan Steel Door for Security Hollow Metal


Awards from Our Partners

Award from Turner Construction

Letter of Recommendation

Wakefield Beasley & Associates

Photos of This Project