Pinellas County Jail - Clearwater, FL

Scope: The Pinellas County Jail Project consisted of upgrades, renovations, and a new addition. The new building is 73,844 gross square feet. It includes a new kitchen, staff dining, laundry prep area, data center, chiller room, generator room, and control room.

Pauly Jail Building Company scope of work included furnishing and installing: security hardware, security hollow metal, security glass, security glazing, detention furniture, security windows, and security mesh.

Start Date: 10/13/2016

PJBC Completion Date: 02/19/2019

Overall Construction Cost: $89,000,000.00

Pauly Jail Building Company Contract Amount: $823,900.00

Construction Manager: Moss & Associates, LLC | 5401 W. Kennedy Blvd., Suite 1060 | Tampa, FL 33609 | (855) 360-6677 Phone | Contact: Brady Kenney, Project Manager

Security Architect: CGL Ricci Greene Architects & Planners | 212 North Upper Street, Suite 130 | Lexington, KY 40507 | (859) 254-5050 Phone | Contact: Jared Altobello

Associate Architect: Mason Blau & Associates, Inc | 4625 East Bay Drive, Suite 228 | Clearwater, FL 33764 | (727) 530-0570 Phone | Contact: Michael Mason

Sheriff: Sheriff Bob Gualtieri | P.O. Drawer 2500 | Largo, FL 33779 | (727) 582-6201 Phone

 

Pauly Jail Building Company self-performs the installation of all detention equipment for every project and is signatory with the International Union of Ironworkers.

Partners that were a part of this project:

- Global Security Glazing for Security Glass

- Kane Innovations, Inc. (Kane Detention) for Security Mesh

- Modern Detention Equipment for Detention Furnishings